Dissertation > Excellent graduate degree dissertation topics show
The Loading Process Research of the Prefabricated Structural Element Continuous Rigid Frame Bridge
Author: YangShouMei
Tutor: JiJing;LiaoHongYan
School: South China University of Technology
Course: Architecture and Civil Engineering
Keywords: Precast segmental Continuous Rigid Frame Bridge BRIDGES force
CLC: U441
Type: Master's thesis
Year: 2010
Downloads: 69
Quote: 0
Read: Download Dissertation
Abstract
|
Bridge segments PREFAB technology in Europe, America and Hong Kong has been widely used [ 1 ] , the Guangzhou Metro Line first large-scale application of segmental precast assembly technology, but the bridge structure system as a simple beam forms a bridge alignment control is relatively simple . As for the bridge precast segments in rigid frame bridge system in the application , at home and abroad than rare . Guangzhou Metro Line Xun Feng Gang ~ River Chassi interval elevated system for dual- walled pier rigid frame bridge, the system piers cast the beam portion using the short method segmental precast technology, field erecting machine suspension assembly . During the construction process has simply supported , consecutive , and then rigid frame system conversion issues , the structural deformation control than the average continuous rigid frame bridge complicated. So carry precast segmental continuous rigid frame bridge system into a bridge with research is particularly important . In this paper, line six elevated structure in the form of design and construction difficulties , focusing on research work . First, in the theoretical analysis by the design parameters of the correction and the actual parameters of the theoretical value affects the sensitivity of the analysis can be derived design parameters and actual parameters of the difference between the theoretical calculated value of not sensitive , which can be obtained the design phase of the parameters used are reasonable ; adopted after the design theory and construction of phase II trial data comparing the results obtained experimental field data and design of the deviation can be controlled within the allowable range , which can be drawn from the design stage using calculation method is reasonable , the results meet the design requirements ; into a bridge after the standard overhead through the precast segments assembled after linear basically meet the design requirements, proved short- matching precast method in the sixth line application is successful. This article by mastering the construction process bridge system by the force acts , from the experimental point of examination of the design and construction program for the real bridge smooth construction of accumulated experience for future similar structure provides a design basis .
|
Related Dissertations
- The Seismic Response of Span Continuous Rigid Frame Bridge in the Long-period Earthquake,U441.3
- - Span continuous rigid frame bridge ultimate bearing capacity and wind resistance research,U441.3
- The Application on Jacking-up Technique in Transformation for Reinforced Concrete Continuous Rigid Frame Bridge,U445.6
- Parameter Sensitivity Analysis and Elevation Control on Long-span Continuous Rigid Frame Bridge,U445.4
- - Span continuous rigid frame bridge construction monitoring and Stability,U445.4
- Risk Losses Research of High Pier and Long Span Continuous Rigid-frame Bridge in the Construction,U448.23
- The Research on Closure Schemes and Long-term Deflection of Multi-span Continuous Rigid Frame Bridges with High Spans,U448.23
- Temperature Effect and Stability Analysis for High-pier and Multi-span Continuous Rigid-frame Bridges,U441.5
- A Study Thesis About the Optimical Design for Ban Shi Continuous Rigid Frame Bridge of Tumen-hunchun Expressway,U448.23
- Finite Element Analysis of Key Mechanical Problems of Continuous Rigid Frame Bridge during Construction,U441
- Vehicles - No ballasted track - the vibration of bridge system,U441.3
- Large Span Continuous Rigid Frame Bridge construction monitoring and simulation analysis,U445.4
- Research on Distinguish Damnify from Span Continuous Rigid Frame Bridges by MSECR,U446
- Analysis of Parameter Sensitivity in Construction Control of Long-span Continuous Rigid Frame Bridge,U445.4
- Prestressed concrete continuous rigid frame bridge construction control study,U445.4
- High Piers of Long Span Continuous Rigid-frame Bridge Construction Control of Elevation and Linear Monitoring,U445.4
- Prestressed concrete continuous rigid frame bridge prestressing reinforcement simulation and construction monitoring,U445.72
- The Construction Supervision Post-evaluation of High Pier and Large-span Continuous Rigid Frame Bridge,U445.4
- Design Parametric Analysis and Research of Multi-span Continuous Rigid Frame Bridge,U448.23
- Analysis on Cracking Mechanism and Prevention Measures of Longitudinal Crack along the Bottom Slab of Long-span PC Continuous Rigid Frame Bridge,U445.7
CLC: > Transportation > Road transport > Bridges and Culverts > Structural principles, structural mechanics
© 2012 www.DissertationTopic.Net Mobile
|