Dissertation > Excellent graduate degree dissertation topics show

The Debugging of Sewage Treatment Plant in Yingshan Country

Author: HuangSiMing
Tutor: KangJianXiong
School: Huazhong University of Science and Technology
Course: Environmental Engineering
Keywords: Debugging Commission C-I-A~2/O process Phosphorus and nitrogen removal
CLC: X703
Type: Master's thesis
Year: 2011
Downloads: 35
Quote: 1
Read: Download Dissertation

Abstract


A~2/O process has been wildly used in municipal wastewater treatment for phosphorus and nitrogen removal. The performance of this process is determined by the quality of the debugging step. However, debugging for the plants is still depending on the experience of the engineers. Therefore, it has important scientific and technological significance to propose some general solutions base on the analysis of the problems and mechanism involved in the process of debugging.The Sewage Treatment Plant of Yingshan County adopted the C-I-A~2/O process. Combining with the situation, we performed the debugging in two stages.The first stage was sludge inoculation and acclimated. After 41 days’sludge inoculation, this stage finished when the SV in Aerobic tank achieved 10%. But results showed that the effluent ammonia nitrogen and phosphorus failed to achieve emissions standards. It may due to the low influent water quantity, low organic matter concentration and low temperature which did not meet the requirements for the cultivation of sludge. And also, we noted that the erosion of sludge and the reflux ratio had not been adjusted on time.The second stage was the official commission stage. After analyzing the problems appeared in the first stage and taking corresponding measures in the second stage, the COD, NH3-N, SS met with B national level discharge standards. However, due to the high concentration of phosphorus in inflow water, improper construction of the sewerage pipeline, and inadequate of sludge removing strength, the total phosphorus (TP) was failed to meet with the national emission standard. Thereby, we proposed several measures, such as strengthening the degree of sludge removing, adding more flocculating agent, adjusting the sludge dewatering equipment.After finished the stage of biological debugging, we adjusted process parameters and debuged overall effluent to achieve effluent standard with the cooperation of structure by keeping the stable quality and quantity of inflow water. In the stable commissioning stage, the operation stability of all the equipments, the impact resistant capacity of structures were monitor on schedule. Whilst, daily management for the operation of the plant such as personnel linkage and establishes handwork arrangement, rules and management system, was also brought into practice.

Related Dissertations

  1. Research on Dam-Break Probability Analysis Method for Dangerous Reservoir,TV697
  2. Construction and improvement of basic education reform process evaluation platform,G521
  3. Implementation Study of evaluation method of the high school IT courses,G633.67
  4. The Design and Implementation of Security Mechanism of Embedded Dependable Computer,TP309
  5. Research on Evaluation of Simulation Systems Based on Fidelity,TP391.9
  6. Research and Application of Digital Assembly Process Planning System for Rocket Engine,TP391.7
  7. Research on Predictive Control and Simulation of pH Value Based on the Confection Process of Sodium Nitrate,TP273
  8. Process Support Vector Machine and Its Application to Satellite Thermal Equilibrium Temperature Prediction,TP183
  9. Study on Extracting Process of Rhizoma Alismatis and Rhizoma Smilacis Glabrae and Their Hypouricemic Effects,R284
  10. On Design of Process-based Collaborative Learning Environment,G434
  11. Research on Index System and Evaluation of University Office Greening,G647
  12. Study on the Synthetic Process of Vat Pink R,TQ616.2
  13. Study on Application of Red Yeast Rice in Fermented Sausage,TS251.65
  14. Study on Synthesis and Physiological Function of N-carbamoyl-glutamate,R914
  15. The Study of Anode Catalyst Pd/C for Direct Formic Acid Fuel Cell,O643.36
  16. Evaluation on Stability of Threshing and Redrying Lamina Structure of Tobacco,TS443
  17. Study on Drying Processing and Sterilization on Spinach,TS255.52
  18. On the Risk Model Involving Two Classes of Claims with Threshold Dividend Strategy,O211.67
  19. Tianjin COSCO Logistics ( Tian Rong ) business process optimization and Countermeasures,F552
  20. A Study on the Performance Improvement Scenario of the Resource Center of China Telecom, Guangzhou Branch,F626
  21. Optimization Study on Gating System and Molding Process Parameters of Injection Mold Based on Simulation,TQ320.662

CLC: > Environmental science, safety science > Processing and comprehensive utilization of waste > General issues > Wastewater treatment and utilization
© 2012 www.DissertationTopic.Net  Mobile