Tribute River Bridge Precamber uncertainty analysis and control
Author: SongYanZuo
Tutor: ZengFangJin
School: Jiangxi University of Technology
Course: Architecture and Civil Engineering
Keywords: Precamber Concrete shrinkage , creep Loss of prestress Temperature changes Calculation of Construction Control
CLC: U445.4
Type: Master's thesis
Year: 2011
Downloads: 31
Quote: 0
Read: Download Dissertation
Abstract
|
Emerging new , larger bridge engineering construction control more and higher requirements . Factors affecting the bridge construction , the complex and there are a lot of uncertain parameter estimation , bridge construction control engineering characteristics vary . Tribute River Bridge project background, research cantilever construction process of shrinkage and creep of the construction Precamber the impact of loss of prestress and temperature changes and other uncertainties . Considering the contribution River Bridge concrete age , humidity , began loading time , the composition of the material and other factors , the establishment of a tribute River Bridge 0-5 block concrete shrinkage and creep of the finite element model to forecast construction in box girder shrinkage and creep the deformation , internal forces , analysis results show that the shrinkage and creep of concrete be smooth bridge closure caused difficulties and cause construction Precamber settings small . Tribute River Bridge superstructure prestress loss calculated correction Practice has proved that the calculation method is reliable, and better meet the prestress loss prediction . Analysis tribute River Bridge No. 5 Box Beam loss linear structure changes and loss of prestress the Bridge Precamber ; combined contribution River Bridge main span Block to the 5th block construction , and the establishment of cantilever construction elements model , cantilever construction of prestressed loss forecast , and provide support for the cantilever Precamber control . Combined contribution River Bridge box girder actual working conditions , to determine the contribution Jiang Bridge box girder structure the distribution of temperature field and temperature difference between stress calculation method ; tribute River Bridge main pier 0 block finite element model , consider the contribution River Bridge cantilever construction of concrete hydration heat, solar radiation , and the effects of temperature changes on the deformation of the bridge structure , stress analysis calculations , bridge construction Precamber determine to provide the basis . Considering the influencing factors Precamber to propose the Gong River Bridge cantilever Precamber . Applicable to calculate the the formulas Practice has proved that the construction given Precamber formula .
|
Related Dissertations
- Study on Deformation Control of Long-span Continuous Rigid Frame Bridge in Construction Stage,U448.23
- Research on the Damping Performance of Tandem Vibratory Rollers,U448.22
- Large Span Prestressed Concrete Continuous Rigid Frame Bridge Analysis and Construction Control of Long-term Practice of Deflection,U448.23
- Stay on Road Performance of Warm Mixture Asphalt,U414
- Research on Pile-Anchor-Soil Interaction of the Anti-slide Pile with Pre-stressed Anchor Cables,P642.22
- Research on Mechanical Behaviors of Unbonded Prestressed Concrete-Filled Square Steel Tubular Structures,TU398.9
- Research on Shrinkage and Creep Effect for High-Pier & Long-Span Continuous Rigid-Frame Bridges,U441.5
- Reaserch on the Long-Term Creep Deflection of Prestressing Concrete Continuous Rigid Frame Bridges,U448.23
- Study on Deflection of Prestressed Concrete Continuous Rigid Frame Bridges,U448.23
- Study on Longitudinal Force of CWR in Ballastless Track on High Speed Railway Long Span Bridge,U213.9
- The Study on Bearing Capacity of the Prestressed Anchor for the Slope Stabilization,TU476
- Study on Creep Property of Prestressed Steel Wire and Applications to Forging Press’ Frame,TG315
- Analysis of extreme temperature changes in Shaanxi Province,P467
- Assessment Methods of Bridge Security Based on Effective Prestressed Detection,U446
- Linear Control of Long-span Continuous Rigid Frame Bridge in Construction Stage,U445.4
- Study on the Key Problems of Construction Control of Extradosed Cable-stayed Bridge,U448.27
- Full-face Formwork Pre-camber Analysis and Design for Continuous Beam Bridge,U448.215
- Research on Long-Term Deformation of Long Span Rigid Frame-Continuous Bridge,U441
- Research on Cable Hoisting Concrete-filled Steel Tube Arch Bridge Arch Rib Alignment Problem,U448.22
- Study on the Long-term Deflection of Long-span PC Continuous Rigid Frame Bridges,U441
CLC: > Transportation > Road transport > Bridges and Culverts > Bridge Construction > Construction Technology
© 2012 www.DissertationTopic.Net Mobile
|