A Decision Method of Concession Period for BOT Projects of Waste Incineration and Generation
Author: SongDanRong
Tutor: SongJinBo
School: Dalian University of Technology
Course: Project Management
Keywords: BOT Concession Period Waste Incineration and Generation Monte Carlo Simulation
CLC: F426.61;F284
Type: Master's thesis
Year: 2010
Downloads: 321
Quote: 3
Read: Download Dissertation
Abstract
|
With Chinese system reform of municipal public utility deepened, BOT (Build-Operate-Transfer) model has been widely used in waste incineration and generation projects all over the country. However, many of them are not well operated as expected because of erratic decision-making, insufficient practical experience of government and project companies, imperfect franchising agreement and etc.Concession period as key issue in BOT projects need to be concerned, not only for theoretical research, but also for practical application. This will affect interests among governments, project companies, publics and some other participants. Moreover, it will also influence development of waste incineration and generation project.Based on above, this dissertation carried out study on a decision method of concession period for BOT projects of waste incineration and generation.Firstly, reviewing literatures concerned concession period for BOT projects and summarizing methods for decision-making model of concession period at home and abroad.Then, with consideration of differences in practical operation cases, a multiple case study is applied to find key risks in our country’s BOT projects of waste incineration and generation. This will provide basis for defining key influencing factors of concession period in waste incineration and generation BOT projects.Furthermore, mathematical modeling method is used to analyze relationships between key influencing factors and concession period. Then, a model and procedures of decision-making for concession period in waste incineration and generation BOT project can be built.Finally, for applying the method of concession period for BOT projects of waste incineration and generation, some basic data is got from a case of waste incineration and generation BOT project in Dalian. This will provide some proposals for governments and project companies in operating BOT projects of waste incineration and generation in the future.
|
Related Dissertations
- The Study on Risk Evaluation of BOT Projects in China University,G647
- BOT financing risk assessment method based on fault tree study,F283
- Study on the Methods of Risk Management in Engineering Project,F224
- The Monte Carlo Simulation in Calculating Credit VaR Based on Improved Credit Transportation Probability Matrix,F224;F832.51
- Application Research of Critical Chain Project Method in Project Schedule Management,F224
- The Research of BOT Application for Municipal Solid Waste Treatment Project,TU993.3
- A Study on the CSI Validity with Simulation,F224
- To run System of BOT financing mode based on the philosophy of engineering,F283
- Research on the Decision Method of Concession Period for Highway BOT Projects,F283;F542
- Designing and Implementation of Garbage Incineration Power Plant Supervisory Information System,TM621.6
- Overseas Investment and Management of Hydropower (BOT) Project,F426.61
- Identification and Control of Retirement Portfolio Ruin Risk,F224
- Guanmin Jiang Directed by Zuoxiang Peng,O21-4
- Nonparametric Two Factor Term Structure Model and Pricing of Interest Rate Derivative,F832.1
- Statistical Diagnostics for Generalized Power Weibull Regression Models with Interval-Censored Data,O212.1
- A Random Weighted Linear Estimator of the ARCH Parameters,F830
- Option Game Analysis of Inner Financed BOT Project in Power Infrastructure,F426.61;F224.32
- Study on Project Finance Model Based on Power Sector,F283
- Pricing Switch-Option-Embedded Notes in a LIBOR Market Model,F224
- Improved maximum priority indicators and in a computerized adaptive diagnostic test application,TP391.76
- BOT investment and financing mode in our stadiums Application,F283
CLC: > Economic > Economic planning and management > Infrastructure the economy > Organization and management of infrastructure
© 2012 www.DissertationTopic.Net Mobile
|