Research on Project Schedule Management System Based on Critical Chain for Software Cooperative Development

Author: WuWenMing
Tutor: ZhangZuPing
School: Central South University
Course: Information and Communication Engineering
Keywords: Software co- development Project Schedule Management Critical Chain Buffer settings
CLC: TP311.52
Type: Master's thesis
Year: 2011
Downloads: 99
Quote: 0
Read: Download Dissertation

Abstract


Software co- development , communication barriers exist due to the geographical dispersion of the developers will lead to the progress of the project there is a big risk , so the good progress of the project management method and system is a must . The progress of the traditional project management methods CPM / PERT ignoring resource constraints and human behavioral factors , there is a relatively large theoretical and technical defects , unable to meet the distributed software collaborative development in the progress of the project management needs . Critical chain method is a further development of the CPM / PERT , developed a more reasonable schedule , the schedule risk management more effective , suitable for software co- development of the project schedule management . Papers According to the characteristics of software co- development , key chain related methods . Recognition of the key chain , the first priority rule - based heuristic algorithm to generate a scheduling plan , and then identify key chain and software co- development of collaborative working relationship on the basis of the analysis , so that collaborative activities can have more synchronization time as the goal, the scheduling adjustment method . In the buffer settings , the smooth transition from to achieve CPM / PERT to the critical chain method point of view, some based on PERT three-point the buffer setting method estimated based on the proposed work together to bring an integrated consideration the uncertainty as well as managers of the level of risk appetite the buffer calculation method , and the problems of the connection buffer is set , the corresponding solution . Finally, the progress of the project management system based on key chain needs analysis, system architecture and database system design , detailed design of the core functions of the system module .

Related Dissertations

  1. Time schedule management in the broadcast monitoring platform construction in the applied research,G221
  2. Study on the Software Project Management of Tax Collecting System,F284
  3. The Study on the Plan and Control of Multi-projects Schedule in Mingzhu FPSO by Critical Chain Method,TU71
  4. Applicaton of Network Planning Technology in Elevator Installation Project,TU721.3
  5. The Application of Critical Chain Project Management in Planning Management of Ship Production,U673.2
  6. Taishan Power Transmission Project Information Research Progress Management System,F283
  7. Research on Critial Resource Conflict Resolution Method in Mould Multi-project,F407.4
  8. Based on the progress of critical chain project management method,F284
  9. The Project Management on Auto Test Software Development of VTECH Group Telecom Company,F407.672
  10. The Applied Research of Critical Chain Method in Schedule Planning of Taihu Ship Lock Project,F284
  11. Research on the Application of Project Schedule Management for Surveying and Mapping Engineering,F284
  12. WT Enterprise 3G business validation Project Management,F626
  13. Research of Project Process Management Based on Critical Chain,F284
  14. Research on the Project Schedule Management Based on the Critical Chain,F284
  15. Powerise Information Technology Company A Project Schedule Management Research,F272
  16. Research on Critical Chain Buffer Placing and Management Based on Float,F284
  17. Research on Time Optimization of Control of the Project about the Making and Contrating of Box Beam of He-Ning Railway Engineering,U213.1
  18. A Study of the Application to Management of Project Scheduling Based on Key Chain Technology in ABB Ltd.,F426.6
  19. Electric vehicle electronic control systems development process Project Schedule Management,U463.6
  20. Zero Inventory Management Base on Schedule Plan of S Enterprise,F253.4

CLC: > Industrial Technology > Automation technology,computer technology > Computing technology,computer technology > Computer software > Program design,software engineering > Software Engineering > Software Development
© 2012 www.DissertationTopic.Net  Mobile